Jun 3, 2004
Edelca starts up Caruachi, Guri turbines
(BNamericas.com) - "State-owned Venezuelan power generator Edelca planned to start operations June of turbine 7 at its Caruachi hydro project and turbine 11 of its Guri hydro plant, the company said in a statement.

Caruachi construction reached 96.7% completion of its civil engineering and electromechanical aspects in May, and operations with all 12 turbines are expected in 2006. With the seventh turbine, annual generation will increase to 10,500GWh.

At Guri, Edelca planned to restart operations of its number 11 turbine in the second power house after replacing parts to improve efficiency. Number 17 is scheduled to restart operations soon after number 11.
Guri is 100km upstream from the confluence of the Caroni and Orinoco rivers and is the second largest hydro plant in the world after the Itaipu plant on the Brazil-Paraguay borde".